May 25

Grout

Will schedule with Martina to rechaulk the grout when they get back.
February 25

Status Report

The parts are in and I am waiting for a schedule to be made so we can finish the kitchen 100%.
February 16

Status Report

The outlets were all changed out and we are waiting for the replacement parts to complete the job 100%
January 23

Status Report

Scott is on site today and should complete the punch list and the change orders that were signed.
January 22

Status Report

Scott will be on site tomorrow to work on the punch list.
 